Executing a job
Jobs for the purpose of server synchronization can be executed automatically according to a schedule, just like other jobs in octoplant.
- To do this, click the Automatic button. This is located in the Configure tab.
- Synchronization is performed according to the schedule you have configured.
To test the job or to synchronize the servers unscheduled, you can also run the job manually.
- Select the job you want from the job list.
- In the ribbon, click on the option Execute job once.
- The job will now be executed.
To stop the job, click on Stop selected jobs.